Microsoft's 10-Q now names 'state and local moratoriums'. The data center next door, in the filings: power, permits and the neighbours

·EvidInvest Team
data centersAI infrastructurepowerpermittingzoningMSFTMETAEQIXCRWVNVDAAMDrisk factors10-QSEC filings

Every company figure and quotation below was read from the companies' own filings on sec.gov and is cited with its accession: the September-quarter 10-Qs (Oracle's and Applied Digital's run to 31 August), the results releases furnished on Form 8-K, and Nebius's Form 6-K. Local and state facts (county votes, court rulings, commission orders, state reports and polls) are not SEC filings. We label them reported and link the primary record. Sums are our arithmetic and are marked (Ours.) Research, not investment advice.

This autumn, one paragraph entered Microsoft's quarterly report. It does not name a chip shortage or a price war. It names the neighbours:

"We also face community opposition, state and local moratoriums, and hyper-local dissent, as well as increasingly coordinated opposition to infrastructure development across jurisdictions, including through the involvement or influence of elected officials, policymakers, and advocacy groups."

That is from the risk factors of Microsoft's 10-Q for the quarter to 30 September (0001193125-26-436133). The same filing records $364.6 billion of datacenter leases signed but not yet started. If you live near a planned campus, or own a company that builds or supplies one, both lines matter.

This is the first post in a series on the build-out at the level of land, power and the town hall.

How to read this post

Three places in a 10-Q carry these lines:

  1. Part II, Item 1A, Risk Factors. A 10-Q only has to show material changes from the annual report, so new wording here is a signal. Oracle's points back to its annual report, Alphabet's adds one paragraph on capacity obligations, and Microsoft, Meta, Equinix, CoreWeave, IREN and AMD restate or add text.
  2. The commitments and leases notes. They show what has been signed and what is still waiting for a building, a grid connection or a permit.
  3. MD&A. It is where delays show up as dates that move.

A risk factor says what could happen; county, court and commission records show what did.

1. Power: the constraint every filer names first

Microsoft (0001193125-26-436133): "The availability, reliability, and cost of electrical power are critical to the operation and expansion of our datacenters. In many regions, electricity generation, transmission, and distribution infrastructure is experiencing increasing demand and capacity constraints." Then: "Limitations in power availability, delays in obtaining power connections, outages, shortages, increased energy costs, or requirements imposed by utilities, regulators, or other market participants could restrict our ability to develop or expand datacenter capacity."

Equinix (10-Q 0001101239-26-000180) reports that it has already run into this: "In certain instances, we have experienced difficulties in securing the energy supply we have contracted for or that we need for our expansion plans."

CoreWeave's 10-Q (0001769628-26-000465) names the price of a connection: "Power providers, other participants in the power market, and regulators may impose onerous operating conditions, such as power generation procurement obligations or collateralization requirements, to any approval or provision of power."

Applied Digital's release (8-K 0001144879-26-000057): "Power remains the gating factor for AI infrastructure".

2. Permits, zoning and the approvals

Microsoft's 10-Q goes past power: "Our ability to develop additional capacity is also subject to land availability, zoning restrictions, environmental reviews, permitting requirements, and other regulatory approvals." A separate bullet describes the rules themselves as already biting: "Emerging laws, regulations, and policies governing the siting, permitting, construction, and operation of datacenters are restricting and delaying infrastructure development, increasing costs, and imposing additional operational and reporting obligations."

Applied Digital (10-Q 0001144879-26-000059) lists "delays or denials of entitlements or permits, including zoning, siting, utility and other permits".

IREN's 10-Q (0001878848-26-000066) is the most specific, because it names the Texas process. It cites delays "as a result of ERCOT's announced amendments to the approval process for large load interconnection requests and the comprehensive verification and audit of all data centers advancing through ERCOT's interconnection process ordered by the Governor of Texas, or as a result of community or public interest advocacy."

The Texas rule behind that sentence is reported in the Public Utility Commission's order in Project No. 58481 (PUCT). Before a large load can be included in an ERCOT interconnection study it must "post financial security in the amount $50,000 per megawatt (MW)". (Ours: $50 million for a 1-gigawatt request before any study runs.) ERCOT's own board update (ERCOT, May 2026) put the queue at "438 GW of Large Load Interconnection Requests". In April it was about 410 GW, "of which ~87% are data centers" (ERCOT, April 2026).

3. The neighbours

Meta (10-Q 0001628280-26-066773): "in the United States, our industry has experienced shifting public sentiment toward data center development, as well as related legislative developments, particularly at the state and local levels."

Equinix: opposition to siting "may lead to delays in permitting and approvals, the imposition of additional conditions, or the cancellation or denial of development opportunities, particularly in areas or jurisdictions with constrained power or water resources or heightened community and public concerns."

CoreWeave names the subjects people object to: "local community opposition and changing sentiment by government regulators relating to data center development, including in response to public concerns regarding electricity and water use, environmental impact and development".

Nebius's shareholder letter, furnished on Form 6-K on 12 November (0001104659-26-126008), is the only filing we found that names the elections: "We will continue listening to communities, working transparently, covering power costs, minimizing water use, and generating tangible community benefits. As a result of our facility design and proactive engagement efforts, we do not anticipate election impacts on our greenfield or co-location sites, including Pennsylvania."

The opinion data behind these sentences is reported. A Heatmap Pro poll by Embold Research (Heatmap, 26 October) found "Seventy-one percent of Americans said they would oppose a data center being built near where they live".

4. Taxes, abatements and bans

Equinix's 10-Q puts local tax policy among the risks: "Changes in public policy toward data centers, including bans, the reduction or repeal of property tax abatements or exemptions or the imposition of new data center-specific taxes or levies, could increase our operating costs and adversely affect the economics of our existing and planned sites."

The size of the exemptions at stake is reported by Virginia itself. Virginia's legislative auditor (JLARC, December 2024): "Data centers and tenants reported saving $928.6 million in sales taxes in FY23 because of the exemption". The state portion, an estimated $683 million, made it "by far the state's largest economic development incentive".

5. Where it already shows up: delays on file

  • CoreWeave (0001769628-26-000465) points to "the delays that we announced in November 2025 with respect to the delivery of certain data centers to be provided by a third-party data center provider". Its lease note sets aside "453 MW of electrical power" not yet delivered at one site and "354 MW" at others, "expected to be delivered in phases between 2026 and 2028".
  • IREN (0001878848-26-000066): "certain contracted capacity that we had targeted to deliver by December 31, 2026 is now expected to be delivered during the following quarter, as a result of a customer-requested design change, supply timing and third-party delays".
  • Nebius (0001104659-26-126008): "Where we rely on third parties, there have been delays. This includes in New Jersey, where we are transitioning the power source to Bloom Energy's sustainable fuel cells." The remaining Microsoft tranches there are "now scheduled for 2Q27".
  • Meta (0001628280-26-066773): "We have changed, suspended, and terminated certain of these projects as a result of various factors".
  • Entergy (10-Q 0000065984-26-000325) has a parish moratorium with an engineering result: "In response to a two-year battery moratorium enacted by the Iberville Parish Council in July 2026, Entergy Louisiana is planning to replace the 200 MW battery planned for the Cypress Harvest Solar facility with a 110 MW battery at the Segno Solar facility and a 90 MW battery at the Votaw Solar facility."

6. The chip makers carry it too

NVIDIA, 10-Q for the quarter to 26 July (0001045810-26-000075; its October-quarter 10-Q was not on EDGAR on 21 November): "The availability of land, power, shell, and capital is crucial to support the buildout of a full data center inclusive of NVIDIA AI infrastructure by our customers and partners". Also: "Power constraints, government actions or regulations, permitting delays, or community opposition may delay, restrict or prevent the development or operation of data centers. We may have limited control over these matters."

AMD, 10-Q for the quarter to 26 September (0000002488-26-000191): "If customers cannot secure sufficient power or water, or experience outages or shortages of these resources, they may be unable to expand their data center capacity and may reduce or stop purchases from us."

NVIDIA entered into guarantees "capped at a total of $105 billion, to provide credit support on a land, power, and shell buildout" for an OpenAI affiliate, "related to leases for approximately 4.25 gigawatts of IT load" in Pike County, Ohio. Its CFO commentary of 17 November (8-K 0001045810-26-000088) lists maximum gross exposure on guarantees of $118.0 billion at 25 October, $105.0 billion of it the SB Energy credit support. AMD reports $13.3 billion of data-center leases not yet commenced that it expects "to assign or sublease to commercial partners", and guarantees of up to $8.5 billion. Alphabet's 10-Q (0001652044-26-000084) records "$75.7 billion of financial support in the form of backstop obligations relating to data centers, including data center lease payments and the associated energy costs for certain agreements."

7. What the local records show

These are reported facts from public records, not SEC filings.

  • Loudoun County, Virginia, home of the cluster Dominion's 10-Q (0001193125-26-440697) calls "the concentration of data centers primarily in Loudoun County". On 18 March 2025 the Board of Supervisors made data centers "a conditional use that now requires an approved special exception… This eliminates data centers as a "by-right" use in the county" (Loudoun County). On 15 September 2026 it voted "to enact a temporary pause on Board consideration of certain legislative applications for data centers and substations", by "a 7-1-1 vote" (supervisor's release on the county site).
  • Prince William County, Virginia. On 31 March 2026 the Court of Appeals of Virginia upheld a finding that the county's hearing notice for the Digital Gateway rezonings was defective, "rendering those rezonings void ab initio" (opinion, copy posted by the residents' group).
  • Tucson, Arizona. On 6 August 2025 the Mayor and Council moved that "we will not consider or approve Project Blue as it has been proposed", and to accelerate "an Ordinance regulating Large Quantity Water Users" (City of Tucson).
  • Coweta County, Georgia. "May 7, 2025 – December 16, 2025 Coweta County's data center moratorium was in effect while the County developed and adopted a data center ordinance" (county staff memo).
  • Port Washington, Wisconsin. The city's development agreement with Vantage lists "$175 million in infrastructure improvements", including water and wastewater capacity, and states "residents will not pay for any costs associated with the project" (city release).

None of these records puts a dollar figure on a delay. The commission orders price the grid connection, and the next post reads them.

What the filings do not say

  • No filer puts a number on community opposition. Microsoft, Equinix and CoreWeave say it "may delay projects", "increase costs" or lead to "the imposition of additional conditions". None sizes it.
  • Amazon's 10-Q (0001018724-26-000040) has no sentence on permits, moratoria or community opposition that we could find. Its risk factors list "resources such as land, water, and energy" among input costs.
  • The leases that wait for all this are large. Leases signed but not yet commenced, as filed: Microsoft $364.6 billion, Meta about $355.73 billion, Oracle $288 billion (0001193125-26-389274, 31 August), Amazon $164,922 million and Alphabet $130.5 billion. (Ours: about $1.30 trillion, on dates a month apart; not a filed total.) Microsoft notes "some arrangements subject to certain contractual conditions being met". Which conditions, it does not say.

Filed this week

Dominion Energy's 8-Ks of the last seven days:

  • 16 November, Item 8.01: an underwriting agreement of 2 November for "$600,000,000 aggregate principal amount" of 5.25% Senior Notes due 2029 and the same amount of 5.95% Senior Notes due 2037 (0001193125-26-462496).
  • 20 November, Item 8.01: the Hart-Scott-Rodino waiting period for its "previously disclosed combination with NextEra Energy, Inc., expired" on 18 November; closing "remains subject to the satisfaction of other closing conditions" (0001193125-26-469339).

Run it yourself

Open the latest 10-Q of a company you follow, go to Part II, Item 1A, and search for "community", "moratori", "permit" and "power". Then find the not-yet-commenced figure in the leases note. This series is about the distance between those two places.

Our leases evergreen explains the not-commenced line. Our Thesis Monitor reads each new filing against the lines you write down and flags the ones that moved. In an agent, the same filings are on the EvidInvest MCP server. It is free to start, credit packs from $10, and there is no subscription.

The neighbours are in the 10-Q now. Read Item 1A before the capex line.

Sources. Microsoft Form 10-Q for the quarter ended 30 September 2026: 0001193125-26-436133. Meta Platforms Form 10-Q, 30 September 2026: 0001628280-26-066773. Alphabet Form 10-Q, 30 September 2026: 0001652044-26-000084. Amazon Form 10-Q, 30 September 2026: 0001018724-26-000040. Oracle Form 10-Q, 31 August 2026: 0001193125-26-389274. Equinix Form 10-Q, 30 September 2026: 0001101239-26-000180. CoreWeave Form 10-Q, 30 September 2026: 0001769628-26-000465. Applied Digital Form 10-Q, 31 August 2026: 0001144879-26-000059, and Form 8-K of 7 October 2026, Exhibit 99.1: 0001144879-26-000057. IREN Form 10-Q, 30 September 2026: 0001878848-26-000066. Nebius Group Form 6-K of 12 November 2026, Exhibit 99.2: 0001104659-26-126008. NVIDIA Form 10-Q, 26 July 2026: 0001045810-26-000075. AMD Form 10-Q, 26 September 2026: 0000002488-26-000191. Entergy Form 10-Q, 30 September 2026: 0000065984-26-000325. Dominion Energy Form 10-Q, 30 September 2026: 0001193125-26-440697, and Forms 8-K of 16 and 20 November 2026: 0001193125-26-462496, 0001193125-26-469339. NVIDIA Form 8-K of 17 November 2026, CFO commentary: 0001045810-26-000088. Reported (not SEC filings): PUCT Project No. 58481; ERCOT board updates (April, May 2026); Loudoun County; Court of Appeals of Virginia (31 March 2026); City of Tucson; Coweta County; City of Port Washington; Virginia JLARC; Heatmap Pro / Embold Research; links in the text. Sources were read on 15 November 2026; EDGAR was re-checked on 21 November 2026. No analyst estimate, consensus figure, share price or price target appears on this page. Research, not investment advice.

EvidInvest is an independent research and information tool. Figures are calculated from public SEC filings and third-party market data and are provided for informational and educational purposes only. EvidInvest does not provide investment advice, brokerage, or financial services, and is not affiliated with any company it covers. Verify all figures against primary sources before making any decision.